Reasonable Endeavours Clauses Can Have Teeth

Unreasonable delay in fulfilling the terms of a contract is an unwise policy, as a recent dispute that ended up in the Court of Appeal shows.

When a developer wished to build an ice-skating rink, its first priority was to secure a clear title to the development site.

The contract entered into with the vendor required the developer to use 'reasonable endeavours' to fulfil certain conditions as soon as reasonably practicable so as to trigger an overage payment of £1.4 million on top of the initial payment made for the purchase of the site.

The additional payment was to have been made within ten working days after the developer was granted 'an acceptable planning permission' as defined in the contract. The initial property transfer was made in 2003 and there was a long stop included that the trigger date had to occur within ten years of the initial contract.

Various negotiations were entered into, but nothing happened that the developer considered would trigger the additional payment until four days after the expiry of the long stop.

The vendor argued that a planning permission that was achieved a few months before the long stop date was an acceptable planning permission, so the overage payment was due. In any event, it argued that the developer's failure to use reasonable endeavours to satisfy the conditions in the contract for payment of the overage caused it a loss. The result was a hearing in the High Court.

The developer argued that the planning permission received before the expiry of the long stop was not an acceptable planning permission because there were some issues still to be resolved relating to property interests, including an easement over the land. The judge commented on this point, saying, "The existence of the easement might be a factor in assessing whether the planning permission was 'commercially viable', but cannot be an unacceptable term or condition of the permission," and concluded that the developer could not reasonably hold the opinion that the terms and conditions of the planning permission were 'unacceptable'.

However, a further condition had to be met (the 'assembly condition'), which was that various leases had to be merged into a superior lease and that lease then merged into the freehold interest.

The case then turned on the reasonable endeavours provision, which involved an examination of the actual behaviour of the developer and led the judge to comment that 'where a party undertakes to use "reasonable endeavours" to achieve an aim he implicitly undertakes not by his own actions to make that aim more difficult of achievement'.

The Court found that the developer had not used reasonable endeavours, but instead had worked to a timetable which meant that the long stop date would pass before the trigger date.

Accordingly, the Court awarded the vendor damages of £1.4 million plus interest, a decision that was recently upheld by the Court of Appeal.

The contents of this article are intended for general information purposes only and shall not be deemed to be, or constitute legal advice. We cannot accept responsibility for any loss as a result of acts or omissions taken in respect of this article.